| Construction of Dual Phase Extraction System |
| |
ProAct
completed construction and prove out of a 51
well dual phase extraction system in 2006 for a major chemical company.
The ground was contaminated with moderate to high concentrations of
naphthalene, phenols, PNA's, and other semi-volatile organic compounds
as a former roofing tar facility. Features of the construction
included:
|
| |
- Building construction
- installation of 51 vapor extraction wells
- 4-20 hp water seal liquid ring pump
- Activated carbon tanks
- Below ground pipe runs
- 51- well manifold
- Electrical components and control panels
- Operation and Maintenance manuals
- System operation prove out
|
 |
 |
 |
 |
 |
 |